The problems encountered during the construction of the rubber track and the treatment measures

 The problems encountered during the construction of the rubber track and the treatment measures

rubber bulging, delamination from the foundation

After the rubber track is finished, local or large-area bulging occurs in a short period of time, or it is separated from the foundation.

Cause Analysis:

If the cement label is unqualified or the basic water and gas barrier is unqualified, the ground water vapor rises and lifts the plastic layer, causing the plastic layer to bulge.

Treatment measures:

Cut off the bubbling part, dry the foundation and do a waterproofing treatment, then fill it up as required, and then fill in the color difference.

Precaution:

Strictly control the quality of basic waterproofing. When laying PU plastic, the basic moisture content and air humidity should be within a safe range.

Foshan GRK Commercial co ltd is focused on PU rubber track on stadium in China ,we are directly manufacture ,we are not only offer materials but also application service.

www.outdoorpaintfloor.com

www.fsgrk.com

WhatsApp:008613660776067

Email:grk-wendy@foshangrk.com.cn

 

Not cured, the surface is sticky

Cause Analysis:

1. During construction, the material ratio error exceeds the safe range, causing the component ratio to be imbalanced, resulting in no cross-linking reaction of the material, which makes the material too viscous or even weak.

2. No hardener is added, or the amount of hardener is too small or the hardener is invalid. These three aspects will cause the material to not be able to fully react and affect the strength of the material.

3. The diluent used is unqualified and contains other impurities, such as alcohols, water, etc., which will hinder the molecular chain when the plastic material reacts, fail to form a polymer, or cause a proportional imbalance.

Treatment measures:

According to the practical situation, decide whether to eradicate and resurface the wet part.

Precaution:

1. Check weighing scales and scales before construction to ensure that their accuracy meets the requirements;

2. Operate strictly in accordance with the construction technical requirements. A small test must be done before construction to determine the quality of the thinner, the quality or the amount of the hardener to avoid unnecessary losses.

Comments

Popular posts from this blog

Daily maintenance and maintenance of the squash court

  Daily maintenance and maintenance of the squash court : Foshan GRK Commercial Co ltd is one of the Chinese sports and commercial flooring supplier. The squash court is an international standard competition venue with a standard width of 6.4 meters, a length of 9.75 meters, a front height of 4.57 meters, a back height of 2.13 meters, a ceiling height of 5-6 meters, a castanets height of 0.48 meters, and a frontal serve line height of 1.83 meters. System: 6mm thick American SPORTWALL elastic swing system, floor system: 18mm thick maple floor, glass back wall system: 12mm thick tempered glass and hardware accessories. So what kind of daily maintenance and maintenance are needed for the squash court : 1. Equipped with professional sports shoes, and put them outside the designated squash court. It is best to equip a few more pairs. There should be carpets or dust-removing mats under your feet. You can't wear shoes directly into the arena from outside, like Leather shoes and rubber sh

Why EPDM granules are the first choice for kindergarten rubber flooring?

  Why do you need to add EPDM granules to the kindergarten rubber flooring? Everyone may be puzzled. In fact, it is beneficial to say that EPDM granules are added to the kindergarten rubber flooring . Why do you say that? Please come and learn about it! EPDM granules are produced from synthetic rubber, which can produce a variety of colors and are resistant to ultraviolet radiation and general chemical reactions with their excellent performance. Used in the kindergarten rubber flooring material, it can increase its flexibility and prolong its life. Especially when there are patterns in the construction, the superiority of EPDM colored granules can be more apparent. Advantages of kindergarten rubber flooring EPDM : 1.  The product can be customized according to user requirements. The color, size, and rubber content of the granules can be customized to meet the different needs of users. 2. Chemical stability Our products have high corrosion resistance and excellent chemical stability,

Stadium standard design plan

  With the continuous development of society, rubber stadium are also entering people’s lives more and more. They are not only a gathering place for a variety of sports, but also a venue for many large-scale events. Let’s look at the optimal plan design for sports. FOSHAN GRK COMMERCIAL CO LTD Contact:Wendy email:grk-wendy@foshangrk.com.cn (1)  Competition items: The IAAF Track and Field Facilities Standard Manual stipulates the standard sports track inner circle circumference is 400 meters, of which the radius of the curve should be 36.5 meters, and the straight road should be along the north-south direction to avoid the dazzling influence when the sun position is low. The curve should have 8 lanes, each lane is 1.22 meters wide, and the straight road has 8 to 10 lanes. The safety area inside and outside the track shall be no less than 1 meter. It is necessary to mark the end position of the competition, mark the position of the obstacle course pool, and mark the intersection of the